How to Compare Multiple Supplier Quotes
Step 1: Write down what you’re buying
Before opening the quotes, write the requirement in one sentence with quantities and scope, such as “40 tonnes of 20mm crushed aggregate and 12 tonnes of washed bedding sand, delivered to site”. Everything else is measured against this. It also stops a quote’s framing from quietly redefining the job.
Step 2: Pick one basis
Choose one unit per item, one GST basis (ex GST if you can claim input tax credits) and one currency. Every quote will be converted to it.
Step 3: Extract every line, with its source
For each quote, list each line item with quantity, unit, rate and amount, and note where it came from (page and line, or sheet and row). Also capture GST treatment, inclusions, exclusions, validity and payment terms. Source references matter when you later need to show someone why you chose a supplier.
Step 4: Normalise
Here is the arithmetic for three synthetic aggregate quotes, each quoting the same requirement differently:
Ridgeline (per tonne, ex GST)
40 t × $48.50 = $1,940.00 12 t × $52.00 = $624.00
Delivery 2 × $185.00 = $370.00 Subtotal $2,934.00
GST $293.40 Total $3,227.40 (10% of $2,934.00 ✓)
Coastal (per kg, inc GST)
Gravel: $0.0572/kg × 1,000 = $57.20/t inc ÷ 1.1 = $52.00/t ex
40,000 kg × $0.0572 = $2,288.00 inc ÷ 1.1 = $2,080.00 ex
Sand: 12,000 kg × $0.0605 = $726.00 inc ÷ 1.1 = $660.00 ex
Freight: TBA → unknown, not zero
Metro (per m³, ex GST)
25 m³ × $78.00 = $1,950.00
8 m³ × $70.00 = $560.00, but the quote shows $590.00 (difference $30.00)
m³ → t needs a density: no tonne comparison without oneIf you wanted to test Metro on a per-tonne basis, you would need a density. For example, a hypothetical 1.6 t/m³ gives $78.00 ÷ 1.6 = $48.75 per tonne, and 25 m³ × 1.6 = 40 t. Change the assumption and the answer changes, so confirm it with the supplier and label it.
Step 5: Check specifications, not just prices
Ridgeline quotes “20mm crushed aggregate”, Coastal “drainage gravel 20mm” and Metro “20mm screened stone”. They share a size, not necessarily a product. Until each supplier confirms the product suits your use, treat those lines as conditional matches rather than equivalents.
Step 6: Compare complete scope and list what’s unknown
Add up what each supplier charges for the whole requirement. Where something is unpriced, excluded or not mentioned, leave it as unknown and say so. In this example only Ridgeline is fully priced, so the honest conclusion is “incomplete”: no overall winner yet, with specific questions to send to Coastal and Metro.
Step 7: Ask, then decide
Turn every gap into a question for that supplier: freight price, product confirmation, the $30.00 line difference. Then compare again. Price is one input. Lead time, validity (Coastal’s is 14 days) and payment terms (30 days EOM vs COD vs 7 days) matter too.
Example data · calculated by the QuantDoc engine
Three aggregate quotes: tonnes, kilograms and cubic metres
What was quoted
- Ridgeline Quarries Pty Ltd: 40 t 20mm crushed aggregate + 12 t washed sand, priced per tonne ex GST, delivery $370 (2 tipper loads).
- Coastal Landscape Supplies: 40,000 kg "drainage gravel 20mm" + 12,000 kg sand, priced per kg inc GST, freight "TBA".
- Metro Aggregates & Hire: 25 m³ "screened stone" + 8 m³ sand, priced per m³ ex GST, delivery included, $35 environmental levy.
INCOMPLETE — Ridgeline Quarries Pty Ltd is the lowest fully-priced quote, but Coastal Landscape Supplies has unknown costs, and Metro Aggregates & Hire quotes a specification not confirmed as equivalent. No overall winner can be declared yet.
Line-by-line matching (4 items)
| Item | Supplier | Match | Normalised rate (ex GST) | Amount (ex GST) |
|---|---|---|---|---|
| 20mm crushed aggregate | Ridgeline Quarries Pty Ltd | Exact equivalent | $48.50 / tonne | $1,940.00 |
| Coastal Landscape Supplies | Conditional match | $52.00 / tonne | $2,080.00 | |
| Metro Aggregates & Hire | Conditional match | — | $1,950.00 | |
| Washed bedding sand | Ridgeline Quarries Pty Ltd | Exact equivalent | $52.00 / tonne | $624.00 |
| Coastal Landscape Supplies | Comparable with adjustment | $55.00 / tonne | $660.00 | |
| Metro Aggregates & Hire | Conditional match | — | $590.00 | |
| Delivery - tipper loads | Ridgeline Quarries Pty Ltd | Exact equivalent | $185.00 / each | $370.00 |
| Coastal Landscape Supplies | Uncertain | — | Unknown | |
| Metro Aggregates & Hire | Uncertain | $0.00 / each | $0.00 | |
| Environmental levy | Ridgeline Quarries Pty Ltd | Missing item | — | Unknown |
| Coastal Landscape Supplies | Missing item | — | Unknown | |
| Metro Aggregates & Hire | Exact equivalent | $35.00 / each | $35.00 |
| Supplier | As quoted (ex GST) | Like-for-like | Complete scope |
|---|---|---|---|
| Ridgeline Quarries Pty Ltd | $2,934.00 | — | $2,934.00 |
| Coastal Landscape Supplies | $2,740.00 | — | Incomplete (delivery unknown) |
| Metro Aggregates & Hire | $2,575.00 | — | Incomplete |
Adjustments recorded
- Coastal Landscape Supplies: Drainage gravel 20mm: 40000 kilogram(s) = 40 tonne(s)
- Coastal Landscape Supplies: Drainage gravel 20mm: GST removed from 2288.00 inc GST → 2080.00 ex GST
- Coastal Landscape Supplies: Bedding sand (washed): 12000 kilogram(s) = 12 tonne(s)
- Coastal Landscape Supplies: Bedding sand (washed): GST removed from 726.00 inc GST → 660.00 ex GST
12 flags raised · 10 clarification questions drafted
- Coastal Landscape Supplies: delivery price to be advised
- Coastal Landscape Supplies: unpriced item
- Metro Aggregates & Hire: possible calculation issue
- Coastal Landscape Supplies: no matching item for "Environmental levy"
- Ridgeline Quarries Pty Ltd: no matching item for "Environmental levy"
- Metro Aggregates & Hire: match needs confirmation
- +6 more
Doing this with QuantDoc
QuantDoc runs steps 3 to 7 for you: extraction with source references, exact unit and GST normalisation, match classification, complete-scope totals that stay incomplete while anything is unknown, flags and drafted clarification questions. You can explore this exact comparison in the live example, or read how it works.
Frequently asked questions
How many supplier quotes should I get?
Three is a common rule of thumb for routine purchases, because it gives you a sense of the range without making comparison unmanageable. What matters more than the number is that every supplier quotes the same scope.
What is the best way to compare quotes in different units?
Convert every price to one unit before comparing. Conversions within a dimension (kg to tonnes) are exact. Conversions across dimensions (cubic metres to tonnes) need a density you confirm with the supplier and record as an assumption.
Should I just pick the lowest total?
Only if every quote covers the same scope on the same GST basis and has no unpriced items. Otherwise the lowest total may simply be the least complete quote.
What else should I compare besides price?
Validity period, payment terms, lead time, inclusions and exclusions, and any arithmetic issues in the quote itself. A cheaper quote that expires in 14 days or requires cash on delivery may not suit you.