Tender levelling

Level every tender against your own scope.

Import your scope of works or bill of quantities as the baseline, upload the tenders, and see each line marked covered, partially covered, missing, excluded, alternative or different quantity, grouped by trade, with every adjustment shown.

Electrical package against the scope

Omissions to price
Scope coverage by subcontractor in the example
Scope lineSub ASub BSub C
30 × Power pointsCoveredPartialCovered
20 × LED light fittingsCoveredAlternativeCovered
1 × Distribution boardCoveredCoveredCovered
Testing and certificationCoveredExcludedMissing
Coverage100%25%75%

Evaluated costs can't be ranked until every omission is priced by the supplier or given a documented adjustment.

Example data: synthetic quotes, real QuantDoc engine output. Open the live example

Why level against a baseline

Comparing tenders with each other only tells you how they differ from one another. If all three leave out the same item, a tender-to-tender comparison won’t show it. Levelling against your own scope or bill of quantities answers the more useful question: what will this tenderer actually deliver for the price, and what is left for you to buy separately?

The traditional way to do that is a levelling spreadsheet: baseline lines down the side, one column per tenderer, and manual notes for every exclusion, quantity difference and lump sum. It works, but every number is retyped, every assumption lives in a comment, and a missed line can swing the result. QuantDoc builds the same matrix from the documents, keeps a source reference for each figure, and records every adjustment it makes.

How each tender is matched to the baseline

Every baseline line receives one status per tender. The statuses are shown in the levelling matrix, grouped by the trade or cost code in your baseline when you provide one.

Covered
The quote prices the baseline line, or explicitly includes it, at the baseline quantity and unit (after exact unit conversion).
Partially covered
The quote covers part of the line, such as supply without installation, or one of several components the line describes.
Missing
The quote doesn’t mention the line. Its cost for that tenderer is unknown, not zero.
Excluded
The quote explicitly excludes the line or the component it depends on, for example “pump by builder”.
Alternative
The quote offers something different from the baseline, such as another grade or product. It is shown, but not levelled as equivalent.
Different quantity
The quote prices the line at a different quantity than the baseline. The difference is shown and can be levelled at the tendered rate.

A levelling calculation, step by step

A small concrete package with four baseline lines and two tenders. Tender B prices less concrete than the baseline, includes edge formwork in its concrete rate and excludes the pump.

Baseline: N32 concrete 24 m³ · SL82 mesh 160 m² · concrete pump 1 item · edge formwork 64 m

Tender A (all lines priced, ex GST)
  Concrete  24 m³ × $255.00 = $6,120.00
  Mesh     160 m² ×   $9.50 = $1,520.00
  Pump                       =   $900.00
  Formwork  64 m  ×  $22.00 = $1,408.00
  Levelled total             = $9,948.00

Tender B (ex GST)
  Concrete  22 m³ × $250.00 = $5,500.00   different quantity
  Quantity levelling: (24 − 22) m³ × $250.00 = $500.00 → $6,000.00
  Mesh     160 m² ×   $9.00 = $1,440.00
  Formwork  included in concrete rate      (covered, no separate price)
  Pump      “by builder”                    excluded → unknown
  Levelled known total       = $7,440.00

Break-even for B’s pump = $9,948.00 − $7,440.00 = $2,508.00
Illustration, hand-worked arithmetic. Tender B is cheaper on levelled scope only if pumping costs you less than $2,508.00 ex GST.

Two judgements sit in that calculation, and QuantDoc keeps both visible. Levelling B’s concrete to 24 m³ at B’s own rate assumes the rate holds for the extra volume, which is worth confirming. Treating formwork as covered relies on B’s statement that it is included in the concrete rate. Both are recorded as adjustments and both feed the clarification questions drafted for Tender B.

Engine example: bundled vs separately priced scope

Tenders don’t always break scope down the same way. Here one supplier quotes supply-and-install as one rate and the other prices tiles and labour separately. The figures below are produced by the QuantDoc comparison engine.

Example data · calculated by the QuantDoc engine

One bundled price vs separately priced supply and labour

What was quoted

  • Supplier A: Supply and install 50 m² carpet tiles at $80/m² ex GST ($4,000).
  • Supplier B: 50 m² carpet tiles at $45/m² ($2,250) plus installation labour at $30/m² ($1,500), ex GST.

Provisional — check before relying on this: Supplier A: no quoted total to check the lines against; Supplier B: no quoted total to check the lines against. Supplier B has the lowest complete-scope cost at $3,750.00 ($250.00 below the next quote).

Line-by-line matching (2 items)
Line-by-line matching, normalised to ex GST
ItemSupplierMatchNormalised rate (ex GST)Amount (ex GST)
Supply and install carpet tilesSupplier AExact equivalent$80.00 / m²$4,000.00
Supplier BConditional match$45.00 / m²$2,250.00
Installation labourSupplier AMissing item—Unknown
Supplier BExact equivalent$30.00 / m²$1,500.00
Supplier totals by view
SupplierAs quoted (ex GST)Like-for-likeComplete scope
Supplier A$4,000.00—$4,000.00
Supplier B$3,750.00—$3,750.00

2 flags raised · 6 clarification questions drafted

  • Supplier B: match needs confirmation
  • Supplier A: no matching item for "Installation labour"
Synthetic example quotes. Figures are computed with decimal arithmetic by the same engine that analyses uploaded quotes. Unknown costs are never treated as zero.

Because Supplier A’s rate bundles installation, its installation component is recorded as included rather than missing, and both tenders reach a complete-scope price. The bundled row is still flagged as a conditional match, so you confirm that “supply and install” covers the same installation work as Supplier B’s labour line before relying on the $250.00 difference.

What you take away

  • A levelling matrix grouped by trade, with a status for every baseline line in every tender.
  • As-quoted, levelled and complete-scope totals, with the comparison labelled INCOMPLETE while any required line is unknown.
  • Break-even thresholds for each gap, so you know which clarifications matter most.
  • A clarification schedule and draft emails per tenderer, which you send yourself.
  • Exports to PDF, Excel and CSV, with source references for every figure.

Baseline levelling is part of the Professional and Business plans. Supported documents are PDFs with a text layer, Excel and CSV; scanned PDFs have limited support.

Frequently asked questions

What format does the scope or BOQ need to be in?

A CSV or Excel (.xlsx) file with a description, quantity and unit for each line. A trade or cost code column is optional and, when present, is used to group the levelling matrix by trade.

Which plans include tender levelling against a baseline?

Scope and BOQ baselines are included in the Professional and Business plans (Professional: up to 300 baseline lines per comparison; Business: up to 1,000 baseline lines per comparison).

Does QuantDoc fill a gap with its own estimate?

No. A missing or excluded line stays unknown unless you enter your own allowance in a labelled scenario. QuantDoc shows the break-even amount at which the ranking would change, and it doesn’t consult external pricing sources.

How are quantity differences levelled?

A different quantity is levelled at the tenderer’s own rate: the difference between the baseline quantity and the tendered quantity, multiplied by that tenderer’s unit rate. The adjustment is recorded so you can see it.

Is the levelling result a recommendation to award?

No. It is a structured comparison with every adjustment and gap visible. Exclusions, qualifications and alternatives are listed as issues for professional review; award decisions remain yours.

Make the next quote comparison clearer.

Upload competing quotes, check the evidence and see what each option really costs.

Free preview, no card required. Paid plans: 60-day trial, card required.