How to Detect Missing Items in Quotes

The cheapest quote is often the one that leaves something out. Here’s how to find the items one quote includes and another doesn’t, and how to work out what the gap could cost.

Why missing items matter

Comparing totals only works when every quote covers the same scope. If one concrete supplier includes pump hire and another doesn’t, the second quote isn’t cheaper. It’s describing a smaller job. You still have to pay for the pump, from that supplier or someone else.

Missing items show up in four ways:

  • Not mentioned. One quote lists an item and another is silent about it.
  • Explicitly excluded. The quote says “excludes freight”, “installation by others” or “traffic control not included”.
  • Listed but unpriced. The item appears with “TBA”, “POA” or “to be advised” instead of a price.
  • Short quantity. The item is there, but for less than you need (16 m³ instead of 18 m³, three weeks instead of four).

A method that catches them

  1. Write down what you need before reading any quote: the materials, delivery, installation, equipment, mobilisation, disposal and anything else the job requires.
  2. Build one list of every line item across all quotes. Each row is one item. Each column is a supplier.
  3. Mark each cell: priced, included in another line, excluded, TBA or not mentioned.
  4. Read the notes and terms. Exclusions are often in the fine print, not in the table.
  5. Never fill a gap with zero. Get a price, or calculate the break-even.

Working out the break-even cost of a gap

When one quote is complete and another has a missing item, you can still say something useful: how much the missing item would have to cost before the ranking changes. Put both quotes on the same GST basis first.

Supplier A (complete, ex GST)
  10 t aggregate × $120.00          = $1,200.00
  Freight                           =   $300.00
  Complete scope                    = $1,500.00

Supplier B (freight TBA)
  10,000 kg × $0.125 inc GST        = $1,250.00 inc GST
  $1,250.00 ÷ 1.1                   = $1,136.36 ex GST

Break-even for B’s freight
  $1,500.00 − $1,136.36             =   $363.64
Supplier B is only cheaper overall if its freight costs less than $363.64 ex GST.

That number is a decision tool. If freight to your site usually costs well over $363.64, Supplier A is likely the better buy even though B’s material is cheaper. If you aren’t sure, ask B for a firm freight price. The same calculation works for a missing item where the other supplier priced it:

Supplier A: 10 m³ N32 × $250 = $2,500 + pump $800 = $3,300
Supplier B: 10 m³ N32 × $240 = $2,400  (no pump mentioned)
If you need a pump: B is cheaper only if its pump < $3,300 − $2,400 = $900
All figures ex GST.

Example data · calculated by the QuantDoc engine

Tonnes vs kilograms, ex vs inc GST, freight to be advised

The engine converts kilograms to tonnes and removes GST, then refuses to declare a winner while freight is unknown.

What was quoted

  • Supplier A: 10 t of 20mm crushed aggregate at $120.00/t ex GST, plus freight $300.00 ex GST.
  • Supplier B: 10,000 kg of 20mm crushed aggregate at $0.125/kg inc GST ($1,250.00), freight "TBA".

INCOMPLETE — Supplier A is the lowest fully-priced quote, but Supplier B has unknown costs. No overall winner can be declared yet.

  • Supplier B is only cheaper than Supplier A overall if its delivery costs less than $363.64.
Line-by-line matching (2 items)
Line-by-line matching, normalised to ex GST
ItemSupplierMatchNormalised rate (ex GST)Amount (ex GST)
20mm crushed aggregateSupplier AExact equivalent$120.00 / tonne$1,200.00
Supplier BComparable with adjustment$113.64 / tonne$1,136.36
Freight to siteSupplier AExact equivalent$300.00 / each$300.00
Supplier BConditional match—Unknown
Supplier totals by view
SupplierAs quoted (ex GST)Like-for-likeComplete scope
Supplier A$1,500.00$1,200.00$1,500.00
Supplier BUnknown (unpriced line)$1,136.36Incomplete (delivery unknown)

Adjustments recorded

  • Supplier B: 20mm crushed aggregate: 10000 kilogram(s) = 10 tonne(s)
  • Supplier B: 20mm crushed aggregate: GST removed from 1250.00 inc GST → 1136.36 ex GST

3 flags raised · 4 clarification questions drafted

  • Supplier B: delivery price to be advised
  • Supplier B: unpriced item
  • Supplier B: match needs confirmation
Synthetic example quotes. Figures are computed with decimal arithmetic by the same engine that analyses uploaded quotes. Unknown costs are never treated as zero.

Example data · calculated by the QuantDoc engine

A line item one supplier didn't quote

Here the requirement didn’t say a pump is needed, so the engine ranks on the concrete. It still flags that Supplier B has no matching pump line, so you can decide whether the pump is part of your scope.

What was quoted

  • Supplier A: 10 m³ N32 concrete at $250/m³ plus concrete pump hire $800 (ex GST).
  • Supplier B: 10 m³ N32 concrete at $240/m³ (ex GST). No pump mentioned.

INCOMPLETE — Supplier A is the lowest fully-priced quote, but Supplier B has unknown costs. No overall winner can be declared yet.

Line-by-line matching (2 items)
Line-by-line matching, normalised to ex GST
ItemSupplierMatchNormalised rate (ex GST)Amount (ex GST)
N32 concreteSupplier AExact equivalent$250.00 / m³$2,500.00
Supplier BExact equivalent$240.00 / m³$2,400.00
Concrete pump hireSupplier AExact equivalent$800.00 / each$800.00
Supplier BMissing item—Unknown
Supplier totals by view
SupplierAs quoted (ex GST)Like-for-likeComplete scope
Supplier A$3,300.00$2,500.00$3,300.00
Supplier B$2,400.00$2,400.00Incomplete

1 flag raised · 3 clarification questions drafted

  • Supplier B: no matching item for "Concrete pump hire"
Synthetic example quotes. Figures are computed with decimal arithmetic by the same engine that analyses uploaded quotes. Unknown costs are never treated as zero.

Where QuantDoc fits

QuantDoc builds the item-by-supplier grid automatically, marks each item as priced, included, excluded, TBA or not mentioned, and labels the comparison INCOMPLETE while any required cost is unknown. It shows break-even thresholds and drafts a clarification question for each gap. Nothing is sent to suppliers automatically. You still decide what your job needs. QuantDoc makes sure nothing silently drops out of the comparison.

Related: identifying missing scope in tenders and scope gap analysis.

Frequently asked questions

If a quote doesn’t mention an item, is it included?

You can’t assume so. Silence means the cost is unknown. It may be included, excluded or simply forgotten. Ask the supplier to confirm in writing before treating it as included.

Should I treat a missing item as zero?

No. Treating an unknown cost as zero makes the incomplete quote look cheaper than it is. Either get a price, use a clearly labelled estimate, or work out the break-even cost at which the ranking would change.

What is a break-even threshold?

It is the most the missing item could cost before the cheaper-looking quote stops being cheaper. It equals the complete price of the other quote minus the known part of the incomplete quote, on the same GST basis.

What does “TBA” or “to be advised” mean in a quote?

The supplier has listed the item but not priced it. It is a known item with an unknown cost, and the quote can’t be compared on total price until it is priced.