How to Identify Missing Scope in Tenders

A tender can be lowest because it’s efficient, or because it’s describing less work. Finding the difference before award is one of the most valuable checks an estimator makes.

Where missing scope hides

  • Exclusions and qualifications. Usually at the end of the tender or in a covering letter: “excludes switchboard”, “traffic management by others”, “rock not allowed for”.
  • Silence. The tender simply doesn’t mention something the job needs. Silence is the hardest gap to see, because there is nothing to read.
  • Unpriced lines. “TBA”, “POA”, “to be confirmed”, or a line with no amount.
  • Provisional sums and allowances. Priced, but as an estimate that may be adjusted, so the final cost is open.
  • Quantity shortfalls. The item is there, but for less than the drawings or BOQ require.
  • Lump sums that hide components. A single figure for “electrical works” may or may not include the switchboard, testing or temporary power.

Gaps that come up again and again

Some items fall between trades so often that they’re worth checking in every package: crane or hoist time, scaffolding, temporary power and water, traffic management, waste removal and tipping fees, after-hours work, testing and commissioning, as-built documentation, and making good after other trades. None of these is unusual. They’re simply easy for each tenderer to assume someone else is covering. If two tenderers both assume that, nobody has priced it.

A practical method

  1. Start from your scope, not from the tenders. List the components the package needs, such as supply, delivery, installation, equipment, mobilisation and disposal, and any trade-specific items. A bill of quantities is ideal if you have one.
  2. Map every tender against that list. For each component mark it priced, included, excluded, TBA or not mentioned.
  3. Read every word of the exclusions and notes, then come back and update the map.
  4. Price or quantify the gaps, using a separate quote, a labelled estimate or a break-even threshold. Never zero.
  5. Send clarification questions to each tenderer about their specific gaps, in writing, before award.

Worked arithmetic: pricing the gap

Electrical package (ex GST)
  A: rough-in $18,400 + fit-off $9,600 + switchboard $4,200 = $32,200
  B: rough-in $17,900 + fit-off $9,100                      = $27,000
     “Main switchboard excluded (by builder)”
  B is cheaper only if the switchboard costs < $32,200 − $27,000 = $5,200

Flooring, 200 m² supplied and installed (ex GST)
  A: supply, deliver and install                      = $12,000 (complete)
  B: supply only, install and delivery excluded       = $10,000
     B cheaper only if install + delivery < $12,000 − $10,000 = $2,000
  C: “delivered”, installation not mentioned          = $11,500
     C cheaper only if its missing scope < $12,000 − $11,500 = $500
Break-even thresholds tell you how much a gap can cost before the ranking flips.

For the flooring, installing 200 m² for less than $2,000 means under $10 per m². That’s worth testing against what installation actually costs you before treating B as the cheapest. For C, a $500 margin leaves almost no room, so C’s installation would have to be close to free.

Example data · calculated by the QuantDoc engine

Two electrical subcontract quotes, one excluding the switchboard

The exclusion is detected and the switchboard line has no counterpart in B’s tender, so no overall winner is declared.

What was quoted

  • Subcontractor A: Rough-in $18,400, fit-off $9,600, main switchboard supply and install $4,200 (ex GST).
  • Subcontractor B: Rough-in $17,900, fit-off $9,100 (ex GST). Exclusion: "Main switchboard excluded (by builder)".

INCOMPLETE — Subcontractor A is the lowest fully-priced quote, but Subcontractor B has unknown costs. No overall winner can be declared yet.

Line-by-line matching (3 items)
Line-by-line matching, normalised to ex GST
ItemSupplierMatchNormalised rate (ex GST)Amount (ex GST)
Electrical rough-inSubcontractor AExact equivalent$18,400.00 / lump sum$18,400.00
Subcontractor BExact equivalent$17,900.00 / lump sum$17,900.00
Electrical fit-offSubcontractor AExact equivalent$9,600.00 / lump sum$9,600.00
Subcontractor BExact equivalent$9,100.00 / lump sum$9,100.00
Main switchboard supply and installSubcontractor AExact equivalent$4,200.00 / each$4,200.00
Subcontractor BMissing item—Unknown
Supplier totals by view
SupplierAs quoted (ex GST)Like-for-likeComplete scope
Subcontractor A$32,200.00$28,000.00$32,200.00
Subcontractor B$27,000.00$27,000.00Incomplete (supply unknown)

2 flags raised · 6 clarification questions drafted

  • Subcontractor B: supply not mentioned
  • Subcontractor B: no matching item for "Main switchboard supply and install"
Synthetic example quotes. Figures are computed with decimal arithmetic by the same engine that analyses uploaded quotes. Unknown costs are never treated as zero.

Example data · calculated by the QuantDoc engine

Supplied-and-installed vs supply-only vs unclear scope

Only Supplier A prices the complete scope. B’s exclusions and C’s silence on installation are both treated as unknown costs.

What was quoted

  • Supplier A: 200 m² vinyl, supplied, delivered and installed: $12,000 ex GST.
  • Supplier B: 200 m² vinyl, supply only: $10,000 ex GST. "Installation and delivery excluded."
  • Supplier C: 200 m² vinyl, delivered: $11,500 ex GST. Installation not mentioned.

INCOMPLETE — Supplier A is the lowest fully-priced quote, but Supplier B, Supplier C have unknown costs. No overall winner can be declared yet.

Line-by-line matching (1 item)
Line-by-line matching, normalised to ex GST
ItemSupplierMatchNormalised rate (ex GST)Amount (ex GST)
Supply and install vinyl flooring incl. deliverySupplier AExact equivalent$60.00 / m²$12,000.00
Supplier BConditional match$50.00 / m²$10,000.00
Supplier CConditional match$57.50 / m²$11,500.00
Supplier totals by view
SupplierAs quoted (ex GST)Like-for-likeComplete scope
Supplier A$12,000.00—$12,000.00
Supplier B$10,000.00—Incomplete (delivery, installation unknown)
Supplier C$11,500.00—Incomplete (delivery, installation unknown)

6 flags raised · 12 clarification questions drafted

  • Supplier B: delivery excluded
  • Supplier B: installation excluded
  • Supplier C: delivery not mentioned
  • Supplier C: installation not mentioned
  • Supplier B: match needs confirmation
  • Supplier C: match needs confirmation
Synthetic example quotes. Figures are computed with decimal arithmetic by the same engine that analyses uploaded quotes. Unknown costs are never treated as zero.

How QuantDoc helps

QuantDoc extracts inclusions and exclusions, checks each required component for every tender, and keeps the comparison labelled INCOMPLETE while any required cost is unknown. It calculates break-even thresholds and drafts a clarification question for each gap. When the scope is set by a bill of quantities, tender levelling against that baseline is covered in comparing a BOQ against subcontractor quotes. Whether a gap is acceptable remains your commercial judgement.

Frequently asked questions

What is a scope gap in a tender?

Work or supply the job needs that a tender doesn’t price. It may be explicitly excluded, simply not mentioned, listed without a price, or priced for a smaller quantity than required.

Is “by others” the same as excluded?

In practice, yes. “By others” or “by builder” means the tenderer won’t do or supply it, so someone else must, and that cost belongs in your comparison.

How do I compare a tender with gaps against a complete one?

Either obtain prices for the gaps, add clearly labelled estimates, or calculate the break-even: the complete tender’s price minus the incomplete tender’s known price. The gap must cost less than that for the incomplete tender to remain cheaper.

Should I reject a tender with exclusions?

Not necessarily. Exclusions are normal. What matters is that every tender is compared on the same complete scope, and that each exclusion is either priced or deliberately accepted.