How to Compare Excavation Quotations

Excavation quotes are hard to compare because the biggest cost drivers (what’s in the ground and where the spoil goes) are uncertain at quoting time. Here is how to compare them on scope and risk, not just the headline figure.

Start with what each quote assumes about the ground

Every excavation price rests on assumptions about soil, rock, groundwater and contamination. Some contractors include an allowance for rock; some exclude it; some carry it as a provisional sum to be adjusted later. Before comparing prices, write down for each quote how it treats each ground risk. Whatever site investigation you have should be in front of every tenderer.

Provisional sums are not fixed prices

A provisional sum is a placeholder. In the worked example below, Supplier A carries rock excavation as a $5,000 provisional sum while Supplier B prices it at a fixed $4,000:

A: $6,800 bulk excavation + $5,000 rock (provisional) = $11,800.00 ex GST
B: $7,400 bulk excavation + $4,000 rock (fixed)       = $11,400.00 ex GST
Quoted difference = $11,800.00 − $11,400.00 = $400.00 in B’s favour

A’s final cost moves with actual rock cost:
  rock costs $3,000 → A = $6,800 + $3,000 = $9,800.00 (A cheaper by $1,600.00)
  rock costs $6,500 → A = $6,800 + $6,500 = $13,300.00 (B cheaper by $1,900.00)
Break-even rock cost for A = $11,400.00 − $6,800.00 = $4,600.00
Hypothetical rock costs, for illustration. Check how the provisional sum is adjusted under your contract.

The question is not “which is cheaper?” but “how likely is rock to cost more than $4,600, and who carries that risk?” Under B’s fixed price, the contractor carries it (subject to the quote’s terms). Under A’s provisional sum, you probably do. How that allocation works under your contract is an issue for professional review.

Check the volume basis for cart-away

Soil increases in volume when excavated (bulking). A quote priced on bank (in-ground) volume and one priced on loose volume are not comparable without a stated bulking factor:

Bank volume 120 m³ × bulking factor 1.3 (assumed) = 156 m³ loose
156 m³ ÷ 10 m³ per truck (assumed) = 15.6 → 16 loads
The bulking factor and truck capacity are assumptions; ask each contractor which they used.

Also confirm whether tipping fees are included, what happens if material is classified as contaminated, and whether the price covers the tip site distance actually available.

Machine size, rates and lump sums

  • Machine size is a specification, not a detail. A 5 t and a 13 t excavator are not equivalent; confirm the size suits access and the work.
  • Hourly or daily rates need an estimated duration to compare with a lump sum. Ask each contractor for theirs, and compare a range rather than a single number.
  • Mobilisation (floating machines in and out) may be separate, included, or per visit. If the job needs two visits, check whether the price covers both.

Items commonly excluded

  • Rock, dewatering and groundwater management
  • Tipping fees, contaminated or acid sulfate soil
  • Service locating and damage to unmarked services
  • Traffic control, permits and road occupancy
  • Shoring, batter stabilisation and compaction testing

Using QuantDoc for excavation quotes

QuantDoc flags provisional sums and allowances as items whose final cost can change, matches line items between quotes with a stated classification, keeps TBA and not-mentioned items as unknown, and drafts questions for each contractor. Conversions such as bank to loose volume or m³ to tonnes are only made with an assumption you enter. The example below is calculated by its engine.

Example data · calculated by the QuantDoc engine

A provisional sum vs a fixed price

What was quoted

  • Supplier A: Bulk excavation and cart away $6,800 lump sum, plus rock excavation as a $5,000 provisional sum (ex GST).
  • Supplier B: Bulk excavation and cart away $7,400 lump sum, plus rock excavation $4,000 fixed (ex GST).

Provisional — check before relying on this: Supplier A: no quoted total to check the lines against; Supplier B: no quoted total to check the lines against. Supplier B has the lowest complete-scope cost at $11,400.00 ($400.00 below the next quote).

Line-by-line matching (2 items)
Line-by-line matching, normalised to ex GST
ItemSupplierMatchNormalised rate (ex GST)Amount (ex GST)
Bulk excavation and cart awaySupplier AExact equivalent$6,800.00 / lump sum$6,800.00
Supplier BExact equivalent$7,400.00 / lump sum$7,400.00
Rock excavation (provisional sum)Supplier AExact equivalent$5,000.00 / lump sum$5,000.00
Supplier BConditional match$4,000.00 / lump sum$4,000.00
Supplier totals by view
SupplierAs quoted (ex GST)Like-for-likeComplete scope
Supplier A$11,800.00$6,800.00$11,800.00
Supplier B$11,400.00$7,400.00$11,400.00

2 flags raised · 4 clarification questions drafted

  • Supplier A: provisional sum
  • Supplier B: match needs confirmation
Synthetic example quotes. Figures are computed with decimal arithmetic by the same engine that analyses uploaded quotes. Unknown costs are never treated as zero.

Frequently asked questions

What is a provisional sum in an excavation quote?

A provisional sum is an allowance for work whose extent isn’t known when quoting, such as rock excavation. The final charge is normally adjusted to the actual cost or measured quantity, so the quoted figure can go up or down. Check the quote and your contract for how the adjustment works.

How do I compare a lump-sum excavation quote with an hourly-rate quote?

Estimate the hours the hourly quote is likely to take, using a stated assumption, and compare the resulting range with the lump sum. Make clear in your comparison that the hourly figure is an estimate, and ask the contractor for an estimated duration.

Why do cart-away prices vary so much between excavation quotes?

Contractors may measure volume differently (in the ground versus loose after excavation), assume different truck sizes and tip sites, and include or exclude tipping fees. Confirm the volume basis, the bulking factor and whether disposal fees are included.

What should I ask an excavation contractor before accepting a quote?

Ask what happens if rock or groundwater is found, whether tipping fees and contaminated material are included, what machine size is allowed, how access and traffic control are handled, and whether the price assumes one mobilisation.